Texas tests Bitcoin miners’ power plans

texas-data-center-grid-lock.jpg



Texas Gov. Greg Abbott ordered the Public Utility Commission and ERCOT to audit every data center project seeking a grid connection before regulators approve any new projects. The order puts AI infrastructure tied to Bitcoin miners under scrutiny, while the audit verifies each project’s power sourcing, water use, cooling plans, and ownership.

The order covers roughly 474 GW of pending connection requests, and Abbott said about 90% of that demand comes from data centers.

That figure runs more than five times the grid’s record peak load. ERCOT paused its Batch Zero transmission-planning study once the order landed, and a separate PUCT survey shows that only 28 of 377 companies responded when asked about their data center plans.

Public Bitcoin miners have spent the past year pitching investors on multi-gigawatt AI infrastructure pipelines.

Those numbers can bundle very different assets under one label, such as raw land near a substation, a queue position still waiting on interconnection studies, and a financed campus already under construction.

Texas just forced a test of that distinction, and FERC is building a matching one at the national level.

Pipeline label What it may actually mean Risk level Investor takeaway
Raw land Site near power infrastructure High Optionality, not capacity
Queue position Project waiting for interconnection review High Exposed to audits, delays and denial
Utility study Power access is being evaluated Medium-high More advanced, but not guaranteed
Approved interconnection Grid path is clearer Medium Valuable, but still needs buildout
Energized substation Power can physically flow Lower Major de-risking milestone
Signed tenant Customer demand is contracted Lower Revenue visibility improves
Project financing Capital stack is secured Lower Construction becomes the main risk
Operating campus Load is live and revenue-producing Lowest Highest-quality capacity

Why Hut 8 is further up the AI infrastructure ladder

Hut 8’s second-quarter numbers show that the company has raised $7.5 billion in project-level financing across two flagship sites, River Bend and Beacon Point, backing 949 MW of contracted IT capacity worth roughly $26.6 billion in expected base-term contract value.

River Bend sits in Louisiana, outside the Texas order entirely. Beacon Point sits in Texas, fully commercialized across roughly 1 GW, and is financed with $4.25 billion in secured notes. It also comes with signed tenants, dedicated financing and construction already underway, a level of de-risking most queue-stage developers cannot match.

Alongside Hut 8’s financed sites, the company reports a roughly 8.66 GW pipeline that still includes capacity under diligence and exclusivity — the less mature rungs of the same ladder.

IREN energized its 1.4 GW Sweetwater 1 site in May, and its existing Childress capacity already backs signed contracts with Microsoft and Nvidia. The company’s filings still warn that ERCOT’s batch review could affect the timing of Sweetwater’s next phase.

About 700 MW of HPC capacity is under Cipher Digital‘s contract, while roughly 2 GW of its Texas pipeline, including the McLennan, Colchis and Mikeska sites, remains subject to that batch process.

MARA’s operating fleet and behind-the-meter power strategy give it a base outside any single approval path. Its proposed 2 GW Matagorda project relies on a different structure, with milestone payments tied to regulatory approval, power authorization and a signed tenant lease.

CleanSpark has a contracted project in Georgia entirely outside ERCOT’s reach. Its Texas sites, 285 MW near Houston and up to 600 MW near Brazoria County, still depend on approvals and power availability that have not yet been secured.

Riot Platforms holds a 700 MW interconnection at Rockdale and an AMD lease that starts at 25 MW, with room to expand toward 200 MW. Its larger Corsicana plan, roughly 600 MW, is still at an earlier stage.

Core Scientific operates about 300 MW of mining capacity at its Pecos campus today, while its plan to expand that site to 1.5 GW rests on power and leases that don’t yet exist.

Company More de-risked assets Assets still exposed to approvals or execution
Hut 8 River Bend and Beacon Point: contracted, financed and under construction 8.66 GW pipeline includes earlier-stage diligence and exclusivity
IREN Sweetwater 1 energized; Childress backs Microsoft and Nvidia contracts Later Sweetwater expansion exposed to ERCOT timing
Cipher Digital Around 700 MW of contracted HPC capacity McLennan, Colchis and Mikeska remain subject to ERCOT batch process
MARA Operating fleet and behind-the-meter strategy Matagorda depends on approvals, power authorization and tenant lease
CleanSpark Contracted Georgia project outside ERCOT Texas sites still depend on approvals, construction and power availability
Riot Platforms Rockdale interconnection and AMD lease Larger Corsicana AI plan remains earlier-stage
Core Scientific 300 MW operating mining footprint at Pecos Expansion toward 1.5 GW depends on future power and leases

Why this reaches past Texas

FERC extended the same logic nationally on June 18, ordering six regional grid operators—PJM, MISO, SPP, CAISO, ISO New England and NYISO—to justify or rewrite their rules for large-load customers like data centers.

Those operators have 60 days to respond to their large-load tariffs and 30 days to explain how they will secure sufficient generation to meet new demand.

That reach already touches miner-built infrastructure outside Texas. Hut 8’s River Bend sits in MISO, MARA’s Long Ridge project sits in PJM, TeraWulf runs major AI capacity in NYISO, and its Abernathy, Texas site connects through SPP’s grid, a separate interconnection queue entirely. Bitdeer is building a 570 MW site in Ohio, also inside PJM.